Developers Meeting on Thurs, July 3, 2025
Time/Location
from 14:00-15:00 UTC
Location: https://lyrasis.zoom.us/my/dspace?pwd=RTk4QUhISnhPRi9YenVrTFJKbDllQT09 (Meeting ID: 502 527 3040). Passcode: dspace
- More connection options available at DSpace Meeting Room
10.0 Release Schedule (TENTATIVE - Not Finalized)
- New Feature Development Deadlines
- Feature PR Creation Deadline: Friday, February 20, 2026
- Feature PR Review/Test Deadline: Friday, March 13
- Feature PR Merge Deadline: Friday, March 27
- 10.0 Release Candidate: Friday, April 3
- 10.0 Testathon: April 6-17 (two weeks)
- 10.0 Translation updates: April 6-17 (during Testathon)
- Bug Fix Deadlines
- Bug Fix PR Creation Deadline: Friday, May 1
- Bug Fix PR Merge Deadline: Friday, May 15
- Documentation & Release Week: May 18-22
- 10.0 Release Announced: Tuesday, May 26, 2026
Agenda
- Discussion Topics - If you have a topic you'd like to have added to the agenda, please just add it.
- DSpace & DSpace-CRIS potential merger discussions
- DSpace and DSpace-CRIS Planning Groups - wiki pages to follow along with ongoing discussions.
- DSpace-CRIS and DSpace Differences - List of known feature/architectural differences between DSpace 8 and latest version of DSpace-CRIS
- DSpace 8.2 and 7.6.4 maintenance releases
- Tentative Release Date of
July 3. July 8 or 9. - Maintenance Board (9.x, 8.x, 7.6.x)
- Tentative Release Date of
- DSpace 10.0
- 10.0 Board: https://github.com/orgs/DSpace/projects/32
- 10.0 Priorities: DSpace Release 10.0 Status (Depends heavily on a final decision around potential merger with DSpace-CRIS)
- Upcoming Refactoring & Modularization Work
- Migration to NX and modularization: https://github.com/DSpace/dspace-angular/pull/4019 (See also DSpace Angular : library-based architecture proposal)
- Upcoming PR from Atmire to make Angular decorators built dynamically again. During migration to Angular standalone components, dynamic builds of decorators were replaced with static maps.
- Other topics
- Question for Angular experts – can we explain more about the transferState changes in PR 3953 ? -kim
- Discuss tests + configuration, where things can go wrong re: https://github.com/DSpace/DSpace/issues/8538 - kim
- DSpace & DSpace-CRIS potential merger discussions
- Board Review:
- 10.0 Project Board - Review PRs collaboratively or Assign new PRs to volunteers to code review and/or test.
- Backlog Board - Are there any tickets here stuck in the "Triage" column? We'd like to keep this column as small as possible.
- Maintenance Board (9.x, 8.x, 7.6.x) - Known bugs can be found here, along with any backported bug fixes.
- Upcoming Topics: (Let us know if there are topics you want to discuss in future weeks)
Attendees
- Tim Donohue
- Holger Lenz
- Giuseppe Digilio (4Science)
- Paulo Graça
- Mark H. Wood
- Grazia Quercia (4Science)
- Corrado Lombardi (4Science)
- Julian Timal (eScire)
- Martin Walk
- Melissa Anez
- Oliver Goldschmidt
- Hrafn Malmquist
- Pascal-Nicolas Becker
- Pierre Lasou
- Kim Shepherd
- Nicholas Woodward
- Sascha Szott
- Marsa Haoua
- Jesiel Viana
- Scholaris Team
Current Work
Project Boards
- DSpace 10.0 board: https://github.com/orgs/DSpace/projects/32
- DSpace 9.x, 8.x and 7.6.x maintenance board: https://github.com/orgs/DSpace/projects/29
To quickly find PRs assigned to you for review, visit https://github.com/pulls/review-requested (This is also available in the GitHub header under "Pull Requests → Review Requests")
Goals for 10.0
To be decided by DSpace Steering Group with feedback from Leadership Group.
Priorities listed at DSpace Release 10.0 Status.
Goals for 8.2 / 7.6.4
Deadline is TBD for both 8.2 and 7.6.4. Bug fix releases do not have fixed/scheduled deadlines. Instead, the developer team will determine when to create a release based on the significance of the issues to solve. (e.g. If major issues are fixed, then a bug fix release will occur more rapidly. If minor issues are found, then a bug fix release may be delayed until sufficient fixes have been made to warrant a release)
- Bug/security fixes only. These minor releases will not include any new features.
- New "themeable components" (for dspace-angular) are allowed in bug fix releases, provided that they don't significantly modify component behavior or similar.
- Accessibility fixes are also allowed in bug fix releases, provided they don't significantly modify component behavior or similar.
- Bug fix PRs should be created against "main" branch where possible. The "main" branch has the most strict code style rules. (i.e. PRs created against
dspace-7_xare becoming more difficult to port forward.) - Per our support policy, bug fixes are only guaranteed to be ported back to 8.x. That said, where possible, we'll try to backport bug fixes (especially significant ones) to 7.6.x.
- Keep in mind, if a specific bug fix is important to you in 7.6.x, then it is best to create two PRs (one for main and one for "dspace-7_x"). If you are able to provide a backport version of the PR, then we will merge it alongside the "main" branch version.
- NOTE: In many scenarios, a backport to "dspace-8_x" should be possible to automate using the "port to [branch]" labels & the "Port merged Pull Request" GitHub Action
Try "Pull Request Trading" for a quicker review
Do you have a PR stuck in "under review" that you really want to see move forward? Or maybe it's someone else's PR but you want to get it more attention?
See Trading reviews on Pull Requests for how to get immediate attention to that PR!
Notes
10.0 Release
- There is a tentative schedule (top of this page), which still needs to be finalized and approved by Steering, DCAT
DSpace & DSpace-CRIS potential merger
- No updates or reports at the moment
- An update about the merger will soon be sent out to the community
Maintenance Releases
- Won't be able to get them out today – there is a security issue that has been reported in DSpace 7.x, 8.x and 9
- We have been digging into that to understand it better and want to apply fixes before releasing maintenance versions
- We are aiming now at July 8 or 9 to get the release out the door
- Because of the extended deadline, there is a little bit more time to get fixes into the maintenance releases
DSpace 10.0
- Lot of bug tickets on 10.0 board if you are looking for anything to do
- Also lots of PRs to review
Upcoming Refactoring & Modularization Work
- Migration to NX and modularization: No updates; further work will occur in the next three weeks
- Restore dynamic component decorators: Art gave update on progress of work
- Q: Where is the map generated? A: in a folder plus one type of DRS files for each decorator
- Giuseppe assigned to PR, Tim will take a look at this as well
- Giuseppe will review Alex's PR and provide feedback
- He will let Tim know if he wants to give an update in an upcoming dev meeting
- Want to try to get these two merged relatively quickly, need to think about which one to merge first
- First phase is split into libraries
- What's the 2nd, 3rd, 4th phase?
- Goal: Get app folder as lean / empty as possible
- For anyone interested to check out how NX works, create a new NX app and play around with it
- There is a wiki page that discusses the NX proposal (as to why to even look at NX)
Other topics
- Question for Angular experts: can we explain more about the transferState changes in PR 3953?
- State refers to NGRX state – before this PR, would transfer state to client (through piece of JSON) and it would have to be done all over again; this PR fixes that
- Q: Is there a situation where we want to set transferState to false? A: In DSpace-CRIS set to false
- It might be useful to document better when to set this to false (and give a reason why)
- If anyone interested in discussing test and config, there is an issue open to clean all of this up
Action items