Background
Resources
Deliverables
Suggested schedule
Develop charter, assemble task force | 4 weeks | week of TBD |
Begin regular meetings | week of TBD | |
Develop action items, assign to team members | 2 weeks | by week of TBD |
Task force development work | 30 weeks | complete by TBD |
Revise deliverables, final review | 4 weeks | complete by TBD |
Members
- Georgy Litvinov - task force lead
- Brian Lowe
- Dragan Ivanovic
Always looking for additional members and developers!
Meeting Times
TBA
Communication Channels
Please join our new slack channel #dynamic-api Slack Channel - contact Georgy Litvinov for more information
- Updates from the task force will be available in VIVO Updates
- Child pages to this page will contain meeting notes