  • Inventory of VIVO assets
  • For each asset, a recommendation regarding future role of the asset.

DRAFT Schedule

 

Task TimelineStatus

Develop charter

2 weeks

2015-03-27 - 2015-04-10

Complete

Solicit members and schedule first meeting

1 week

2015-03-27 - 2015-04-03

Complete

Determine asset attributes

2 weeks

2015-04-06 - 2015-04-16

Complete

Solicit VIVO community regarding assets

2 weeks

2015-04-20 - 2015-05-08

 

Review assets, preliminary recommendations

2 weeks

2015-05-11 - 2015-05-22

 
Final recommendations2 weeks2015-05-25 - 2015-06-05 

 

Members

Mike Conlon VIVO Project Director – facilitator (Skype mike.conlon17)

...

Alex Viggio Symplectic – member (Skype aviggio)

Meeting Times

Kick off meeting on Wednesday, April 8 on Skype at 2:30 Eastern.  If there are technical issues, please email me mconlon@ufl.edu, or Skype chat to mike.conlon17.

Follow up meetings TBDAs needed.  First meeting April 8.  Follow-up April 15.  Third meeting TBD. Contact Mike Conlon as needed.

Communication Channels

  • Distribute proposed charter and solicit participation from community via appropriate mailing list

  • Announce task force creation and progress on relevant Working Group calls.

  • Create a page in the VIVO wiki (wiki.duraspace.org), with child pages for agenda, notes, and additional information

  • Solicit information from the community regading VIVO assets via appropriate mailing lists

...