Background
Resources
Deliverables
- Phase I
- Questionnaire and Results Analysis
- Phase II
- TBD
Suggested schedule
Develop charter, assemble task force | 4 weeks | week of TBD |
Begin regular meetings | week of TBD | |
Develop action items, assign to team members | 2 weeks | by week of TBD |
Task force development work | 12 weeks | complete by TBD |
Revise deliverables, final review | 4 weeks | complete by TBD |
Members
Ralph O'Flinn - task force lead
Looking for additional members and developers
Meeting Times
TBD (Fall 2020)
Communication Channels
Please join our new slack channel #dataingest - contact Ralph O'Flinn for more information
Updates from the task force will be available in VIVO Updates
- Child pages to this page will contain meeting notes