Tasks | Duration | Start | End | Status/Notes | ||
Develop charter, requirements, resource feasibility, solicit participation, approval of steering, project infrastructure, launch sub projects | 3 weeks | 2016-01-24 | 2016-02-13 | All complete except infrastructure. Mike Conlon working on this. On track. | ||
Domain name, infrastructure hosting, stand up platform, three tier build, branding | 4 weeks | 2016-02-02 | 2016-3-06 | Domain openvivo.org obtained. Infrastructure provider identified. Graham Triggs working on this. On track. | ||
ORCiD authentication, Profile creation, ORCiD hook for DOI | 6 days | TBA | TBA | Jim Blake will work on this. On track. | ||
RDF generation for Journals (CrossRef) and Organizations (Grid) | 4 weeks | 2016-02-13 | 2016-03-13 | Muhammad Javed will work with Mike Conlon on Journals. David Eichmann will work with Mike Conlon on Organizations. Alexandre Rademaker will also help. | ||
Figshare Ingest | 4 weeks | 2016-02-13 | 2016-03-13 | Ted Lawless will work with Mike Conlon on this. | ||
Publication Ingest from CrossRef with Attribution from user-entered DOI | 5 weeks | 2016-02-07 | 2016-03-12 | Graham Triggs is working on this. Prompt, fetch, confirm working. On track. | ||
Full assembly – all features in place. Begin testing, begin remediation, begin data export | 1 week | 2016-03-13 | 2016-03-19 | Tight coordination among team members needed here. | ||
Remediation or additional features | 2 weeks | 2016-03-20 | 2016-04-02 | If things need to be fixed, fix them. If things need to be smoothed, smooth them. If things can be added, add them. | ||
Final acceptance testing, refinement, communications, presentation materialsHarvest data from Open VIVO to CTSAsearch | 2 weeks | 2015-0403-0320 | 2015-04- | 15Harvest data from Open VIVO to CTSAsearch | 02 | Dave Eichmann will work on this |
Final acceptance testing, refinement, communications, presentation materials | 2 weeks | 2015-04-03 | 2015-04-15Dave Eichmann will work on this | Stop adding things. Keep fixing things. Keep smoothing things. | ||
Workshops and Visualizations Hackathon at Force 11 Conference | 1 day | 2016-04-17 | 2016-04-17 | |||
Additional Force11 demonstrations, continuous update of open VIVO from Figshare and ORCiD, continuous export of data to GitHub, continuous import of data to Iowa repositories and tools. | 2 days | 2016-04-18 | 2016-04-19 |
...