Tasks | Duration | Start | End | Status/Notes |
Develop charter, requirements, resource feasibility, solicit participation, | 3 weeks | 2016-01-24 | 2016-02-13 | All complete except infrastructure. Mike Conlon working on this. On track. |
Domain name, infrastructure hosting, stand up platform, three tier build, | 4 weeks | 2016-02-02 | 2016-3-06 | Domain openvivo.org obtained. Infrastructure provider identified. Graham Triggs working on this. On track. |
ORCiD authentication, Profile creation, ORCiD hook for DOI | 6 days | TBA | TBA | Jim Blake will work on this. On track. |
RDF generation for Journals (CrossRef) and Organizations (Grid) | 4 weeks | 2016-02-13 | 2016-03-13 | Muhammad Javed will work with Mike Conlon on Journals. David Eichmann will work with Mike Conlon on Organizations. Alexandre Rademaker will also help. |
Figshare Ingest | 4 weeks | 2016-02-13 | 2016-03-13 | Ted Lawless will work with Mike Conlon on this. |
Publication Ingest from CrossRef with Attribution from user-entered DOI | 5 weeks | 2016-02-07 | 2016-03-12 | Graham Triggs is working on this. Prompt, fetch, confirm working. On track. |
Full assembly – all features in place. Begin testing, begin remediation | 1 week | 2016-03-13 | 2016-03-19 | Tight coordination among team members needed here. |
Remediation or additional features | 2 weeks | 2016-03-20 | 2016-04-02 | If things need to be fixed, fix them. If things need to be smoothed, smooth them. If things can be added, add them. |
Final acceptance testing, refinement, communications, presentation materials | 2 weeks | 2015-04-03 | 2015-04-15 | |
Workshops and Visualizations Hackathon at Force 11 Conference | 1 day | 2016-04-17 | 2016-04-17 | |
Additional Force11 demonstrations, continuous update of open VIVO from | 2 days | 2016-04-18 | 2016-04-19 |
...