UI Deliverables:

Deliverable

Date

Status

Define the simplified flow for Phase 1 in the form of a revised flow chart

May 28

(warning)

Review the revised flow chart and open items

May 28

(warning)

Finalize the revised flow chart and open

June 4

(warning)

Develop initial wireframes based on the finalized flow chart

June 11

(warning)

Review the initial wireframes

June 18

(warning)

Finalize the wireframes

June 25

(warning)

Develop mock-ups for each screen

July 2

(warning)

Review mock-ups

July 9

(warning)

Deliver final mock-ups and image assets

July 16

(warning)

Timeline

This timeline documents the DGI/SI/DuraSpace cross-team collaboration activities for iteration 0.2.

Milestone

Due Date

Owner

Status

Design Islandora/DfR AMI: account?, instance size?, EBS?, S3?, etc

May 29

Rick/Gervais/Andrew

(tick)

Create Islandora/DfR AMI: account

May 29

Rick/Gervais/Andrew

(tick)

Define DfR Content Model

June 1

DGI/Dan/Chris

In Process

Login to Islandora/DfR instance

June 1

DuraSpace

(tick)

Ingest test objects via SI

June 7

DuraSpace

(warning)

Ingest test objects via OCS

June 7

Dan/Chris

(warning)

View content in Islandora/DfR instance

June 15

DuraSpace

(warning)

DfR 0.2

July 16

DuraSpace

(warning)