UI Deliverables:
Deliverable |
Date |
Status |
---|---|---|
Define the simplified flow for Phase 1 in the form of a revised flow chart |
May 28 |
|
Review the revised flow chart and open items |
May 28 |
|
Finalize the revised flow chart and open |
June 4 |
|
Develop initial wireframes based on the finalized flow chart |
June 11 |
|
Review the initial wireframes |
June 18 |
|
Finalize the wireframes |
June 25 |
|
Develop mock-ups for each screen |
July 2 |
|
Review mock-ups |
July 9 |
|
Deliver final mock-ups and image assets |
July 16 |
|
Timeline
This timeline documents the DGI/SI/DuraSpace cross-team collaboration activities for iteration 0.2.
Milestone |
Due Date |
Owner |
Status |
---|---|---|---|
Design Islandora/DfR AMI: account?, instance size?, EBS?, S3?, etc |
May 29 |
Rick/Gervais/Andrew |
|
Create Islandora/DfR AMI: account |
May 29 |
Rick/Gervais/Andrew |
|
Define DfR Content Model |
June 1 |
DGI/Dan/Chris |
In Process |
Login to Islandora/DfR instance |
June 1 |
DuraSpace |
|
Ingest test objects via SI |
June 7 |
DuraSpace |
|
Ingest test objects via OCS |
June 7 |
Dan/Chris |
|
View content in Islandora/DfR instance |
June 15 |
DuraSpace |
|
DfR 0.2 |
July 16 |
DuraSpace |
|