Dates
- Final Sloan submission: March 1, 2013
- Demo Date: Jan 28, 2013
- Code Freeze: Jan 18, 2013 (noon)
Items to be delivered to Sloan:
- DfR Source Code
- DfR presentations
- Documentation
- Executive Summary (1-2 page overview)
- Final Report (<= 10 pages. Project goals, accomplishments, challenges, outputs. Very similar to content of final Sloan presentation/demo)
- Financial Report
- Technical Strategy (previously called 0.3 System Overview)
- Use Case listing
- Invitational workshop report
- Wiki docs (link)
- JIRA listing (Structure, Top Level)
Technical TO DO
Description | Assignee | Status |
---|---|---|
Verify that all code has appropriate headers | Dan | Nearly Complete (To finish week of 2/25) |
Test code against DuraCloud 2.3, update as necessary to build/run properly | Dan | Awaiting 2.3 |
Tag 0.3 code release | Dan | Post 2.3 Tasks |
Documentation TO DO
Description | Assignee | Status |
---|---|---|
Organize JIRA listing (ensure items are closed and sorted) | Dan | This facilitates documenting user stories. Just need to check traceability (To finish week of 2/25). Estimate 4 hours remaining. Structure: https://jira.duraspace.org/secure/StructureBoard.jspa?s=102 |
Open up permissions to JIRA and wiki space | Dan/Bill | |
Finalize Technical Strategy doc
| Dan (with input from team) | Need completed first review (doc is ready) I am leaving in red editorial marks for now until Jonathan and Bill have a chance to read (unless you prefer to put both version side by side). Feel fred remove them if you are satisfied. In wiki form for now, convert links to footnotes with a document form is created. Estimate 2 hours remaining. |
Provide bulleted listing of technical achievements for Final Report | Dan | |
Write Executive Summary
| Jonathan | Dan can help write when outline Ok'd |
Write Final Report | Jonathan | In process |
Organize wiki docs before export (as needed) | Dan | Waiting until all documentation is completed. Planning move to public Wiki as deliverable (can generate PDF) |
Collect DfR presentations | Jonathan | |
Organize use case listings | Dan/Jonathan | Dan has started. Estimate 8hrs remaining. Organizing JIRA first though text for Epics has been added to the Wiki page. Stories are next, then working descriptive format. |