Developers Meeting on Weds, January 12, 2011
Agenda
- First 15-20 minutes: JIRA Catch-Up – starting with issue DS-651
- Beginning to Plan Next Releases
- DSpace 1.7.1 - Needs a Release Coordinator (and tentative schedule)
- DSpace 1.8.0 - Needs a Timeframe and a Release Coordinator
- Thoughts on a 1.8.0 Timeframe: 6 months? 9 months (same as 1.6.0->1.7.0)? 12 months?
- Possible, sample 9 month timeframe (similar to 1.7.0's schedule):
- May 13, 2011 : "Beta 1"? (Milestone 1?)
- June 3, 2011 : "Beta 2"? (Milestone 2?) - Note: OR11 is June 7-11
- July 22, 2011 : Feature Freeze?
- July 29, 2011 : Final Documentation "Due Date"?
- August 5, 2011 : Release Candidate 1?
- August 8-19, 2011 : Testathon?
- September 2, 2011 : Release Candidate 2?
- September 5-14, 2011 : Final Testing / Bug Fixing?
- September 16, 2011 : Final Release?
- Topics for upcoming "Special Topics" Meetings?
- git / DCVS