Proposed timeline

The first phase

  • Application deadline - January 17th
  • First round of selection/review results - January 24th
  • Interviews as needed - February 7th
  • Final selection - February 10th
  • Implementation - February 14th - May 14th
  • Reviewing of developed code - May 28th
  • Code correction - June 21st
  • Documentation- June 30th

...

All interested applicants should submit a short CV and letter of interest via vivo@lyrasis.org email by January 17th. The application is only for the first phase of the project, although selected candidates will have priority in the negotiation for the second phase of the project.  

...