Page History
...
- (30 mins) General Discussion Topics
- Any final OR2021 prep/questions from anyone?
- Setting a release date for 7.0
- Assuming only "high priority" tasks (~80hrs of estimated dev work). "Medium priority" tasks become "nice to have", but many/most will be delayed to 7.1
- Tentative Dates for 7.0 Final release:
- Monday, Aug 2: Public Release DateDeadline
- Internal Release Goal: Monday, July 26 (i.e. we will release early if possible to do so)
- July 15: every 7.0 PR merged
- June 24 - July 15 code reviews & PR updates (Art out week of July 12, Ben out week of July 5, Tim out week of July 5, Andrea out June 23-July 2)
- June 24: every PR created (high priority mainly) - Guaranteed . Any created by this date are "guaranteed" in 7.0, anything . Anything after may not be included in 7.0.
- Monday, Aug 2: Public Release DateDeadline
- Ranking of outstanding 7.x features (by DSpace Governance): DSpace Release 7.0 Status#7.x
- (30 mins) Planning for next week
- Review the Backlog Board - Are there any tickets here stuck in the "Triage" column? We'd like to keep this column as small as possible.
- Review the 7.0 Project Board - Assign tickets to developers & assign PRs to reviewers.
- Priority should be kept in mind here. If new "high" or "medium" priority tickets come in, developers should move effort off of "low" priority tasks. Reviewers/testers should also concentrate effort on "high" or "medium" priority PRs.
...