Phased development plan has been created (phase 1, 2 and 3)
Phase 1 items are working
Phase 2 have been implemented but need more testing
Phase 3 have not yet been implement.
So export works well but not between versions
Import works but needs more testing
Importing to a different URL doesn't work
Timestamps and other internally managed values require some work (lossiness)
Import and export bags is implemented but needs testing and need to verify that it meets the standards of AP Trust
At a high level: round-tripping to an empty repository or container seems to work.
Non-empty containers is a possibly a problem.
Export follows LDP contains relationship by default and allows for specifying custom predicates for defining the boundary of the hierarchy of resources
Verification tool:
works but could use improvement
A couple of issues:
We don't deal with the server managed triples
We need to figure out how to handle those
Tied to the issue of lossy import.
Commandline interface: We need to improve the responses from the command line tool
Unicode escaped strings in RDF are fool the tool into seeing a failure where no failure is.