TasksDurationStartEndStatus/Notes

Develop charter, requirements, resource feasibility, solicit participation, approval of steering, project infrastructure, launch sub projects

3 weeks

2016-01-24

2016-02-13All complete except infrastructure. Mike Conlon working on this. On track.

Domain name, infrastructure hosting, stand up platform, three tier build, branding

4 weeks

2016-02-02

2016-3-06Domain openvivo.org obtained. Infrastructure provider identified. Graham Triggs working on this. On track.

ORCiD authentication, Profile creation, ORCiD hook for DOI

6 days

TBA

TBAJim Blake will work on this. On track.
RDF generation for Journals (CrossRef) and Organizations (Grid)4 weeks2016-02-132016-03-13

Muhammad Javed and Violeta Ilik will work with Mike Conlon on Journals. David Eichmann will work with Mike Conlon on Organizations.

Figshare Ingest4 weeks2016-02-132016-03-13Ted Lawless will work with Mike Conlon on this.
Identify and represent attribution/contribution4 weeks2016-02-132016-03-13Melissa Haendel, Kristi Holmes, Violeta Ilik and Alexandre Rademaker will work on this.
Publication Ingest from CrossRef with Attribution from user-entered DOI5 weeks2016-02-072016-03-12Graham Triggs is working on this. Prompt, fetch, confirm working. On track.
Full assembly – all features in place. Begin testing, begin remediation, begin data export1 week2016-03-132016-03-19Tight coordination among team members needed here.
Remediation or additional features2 weeks2016-03-202016-04-02If things need to be fixed, fix them. If things need to be smoothed, smooth them. If things can be added, add them.
Harvest data from Open VIVO to CTSAsearch2 weeks2015-03-202015-04-02Dave Eichmann will work on this

Final acceptance testing, refinement, communications, presentation materials

2 weeks

2015-04-03

2015-04-15Stop adding things. Keep fixing things. Keep smoothing things.

Workshops and Visualizations Hackathon at Force 11 Conference

1 day2016-04-172016-04-17 

Additional Force11 demonstrations, continuous update of open VIVO from Figshare and ORCiD, continuous export of data to GitHub, continuous import of data to Iowa repositories and tools.

2 days2016-04-182016-04-19 

 

...