Date | Milestone | What it means |
---|---|---|
October 06 | Deadline for feature pull requests | If you wish to contribute features to DSpace 5.0, you must submit a pull request by this date. |
October 08 | Weekly developers' meeting devoted to review of feature pull requests for 5.0 | The entire hour's meeting will be used to discuss proposed features submitted by the deadline. |
October 15 | Weekly developers' meeting devoted to review of feature pull requests for 5.0 | The entire hour's meeting will be used to discuss proposed features submitted by the deadline. |
October 2027 | Feature freeze | DSpace 5.0 is considered feature-complete on this date. Only bugfixes will be pulled between this date and final release. |
October 31 | Release Candidate 1 tagged | A DSpace 5.0 Release Candidate will be available for wider testing. |
November 03-14 | Testathon | Intensive public testing of the 5.0 Release Candidate is invited. The Release Team will focus on getting problems resolved. |
November 20 | Release Candidate 2 tagged | An updated DSpace 5.0 Release Candidate will be available for wider testing. |
Early to mid December | DSpace 5.0 is publicly released | DSpace 5.0 is released for download and general use. |
...