  1. Meta analysis of sprint process
  2. Summarize final state
  3. Walk through in-process and unstarted tickets
  4. Teeing up for next sprint

Minutes

Sprint Analysis

  • Esme
    • Sprint went smoothly
    • Should have updated beta pilot ticket more frequently
    • Will be on Penn State sprint next week
      • Will fix Fedora 4 bugs during this sprint
      • Goal is to get Hydra Sufia RC on Fedora 4
  • Jon
    • Sprint process works well
    • Would like to be more productive
      • Difficulties working in a Windows environment
      • Some internal meetings pulling at attention. Context switching is difficult
  • Andrew
    • Productive sprint
    • Long list of tickets to be reviewed
    • Someone needs to be aware of everything going into the codebase. Right now this is Andrew, but this creates a bottleneck
      • For the long term, this will need to be revisited
    • Wondering about motivations for getting involved in the sprints
      • Esme 
        • Initially told to work on the project
        • Desire to get away from custom system and join community
      • Jon
        • Using Islandora and mostly relying on vendor support
        • Desire to become more self-reliant and learn more about Fedora
        • Using the sprints as a training opportunity
    • Making a number of unassigned issues available to be worked on gave Osman an opportunity to dive in and resolve many of these issues quickly
  • David
    • How to get help when questions aren’t getting answers
      • Hard to ask questions when you are new
      • Encourage sprint participants to help each other