  • agenda review
  • Status of code base merge (Matt) - 10 min
    • in process for de-branding Libra - taking till end of the week
    • now appears that this is no longer Hydrus task....
    • waiting on rails 3 upgrade - Matt to talk to Tom Cramer
    • will be working on code branch for Hydrus that will have either....
  • JIRA review of 0.0 version tickets (All) - 30 min
    • All 0.0 tickets
    • what is missing for 0.0 environmental setup?
    • sequence of work for 0.0
  • if time remaining prepare for 0.1 - 15 min

Action Items

  • Matt and Tom need to have conversation to confirm moving Rails 3 upgrade to April and SOW for March.
    • Matt estimates that this will take 20-25 developer hours - won't be able to happen in March
      *