Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Initially all candidate issues for Fedora 3.4 should have Fedora 3.4 as the "Fix version(s)"
  • At the start of a milestone
    • Review any newly-submitted issues, and either
      • Assign to "Fix version(s)" Fedora 3.4 if appropriate, and open; or
      • Assign to a future fix version if appropriate, and open; or
      • Close/won't fix if appropriate; or
      • Leave as submitted if not possible to make a decision
    • Prioritise all issues in "Fedora 3.4"
    • Move highest-priority issues into next milestone
    • Ensure all issues in next milestone are assigned
    • Ensure all issues in next milestone have a tester assigned
    • Review workload, add more issues from "Fedora 3.4" or move issues back to "Fedora 3.4" until milestone looks do-able
  • During the milestone
    • Work on issues, according to who's assigned
  • At the end of the milestone
    • Ensure completed items have been tested
    • Ensure completed items are marked completed
    • Move any unstarted issues back to "Fedora 3.4"
    • Move any work-in-progress items to the next milestone (question)

To do: can we have a hierarchical "Fix version(s)" structure, ie Fedora 3.4->Milestone 1; or should we use a separate custom "Milestone" field?

Candidate timetable

Candidate timetable

Weeks run from Tuesday through to Monday of the following week, to coincide with the regular Committers Meeting on Tuesday of each week, during which activites of the previous week can be reviewed, and activities for the coming week can be planned.

Week

Deadline

Activity

Apr 20 (Tue) - Apr 26 (Mon)

Mon 26 April -

Date (week commencing)

Deadline

Activity

29 Mar

 

Release preparation/planning

05 Apr

 

Release preparation/planning

12 Apr

Friday -  Milestone 1 scheduled

Release preparation/planning

19 Apr Apr 27 (Tue) - May 3 (Mon)

 

Work on Milestone 1 items 26 Apr

May 4 (Tue) - May 10 (Mon)

 

Work on Milestone 1 items

May 11 (Tue) - May 17 (Mon)

Mon 17 May

03 May

Friday - Milestone 1

Work on Milestone 1 items

10 May May 18 (Tue) - May 24 (Mon)

 

Work on Milestone 2 items

17 May May 25 (Tue) - May 31 (Mon)

 

Work on Milestone 2 items

Jun 1 (Tue) - Jun 7 (Mon)

Mon 7 Jun

24 May

Friday - Milestone 2

Work on Milestone 2 items 31 May

Jun 8 (Tue) - Jun 14 (Mon)

 

Work on Milestone 3 items

07 Jun Jun 15 (Tue) - Jun 21 (Mon)

 

Work on Milestone 3 items

Jun 22 (Tue) - Jun 28 (Mon)

Mon 28 Jun

14 Jun

Friday - Milestone 3 - RC Code Freeze (code freeze)

Work on Milestone 3 items

Jun 29 (Tue) - Jul 5 (Mon)

Fri 2 Jul - RC release

21 Jun

Friday - RC Release

Release week - final testing and release 28 Jun

Jul 6 (Tue) - Jul 12 (Mon)

 

Keep clear, week before OR2010

05 Jul

 

OR2010

OR2010 5-9 Jul

Jul 13 (Tue) - Jul 19 (Mon) 12 Jul

 

RC testing (community)

19 Jul Jul 20 (Tue) - Jul 26 (Mon)

 

RC testing (community)

26 Jul Jul 27 (Tue) - Aug 2 (Mon)

 

Bug fixes

02 Aug Aug 3 (Tue) - Aug 9 (Mon)

 

Bug fixes

Aug 10 (Tue) - Aug 16 (Mon)

Fri 13 Aug

09 Aug

Friday - 3.4 Release

Release week - final testing and release