- Work to be done by mid-term evaluation
- Work to be done by end of GSOC
- Documentation to be generated
Draft
The following draft outlines a proposal for the project plan. It has to be approved in a meeting with the community:
- 24th May - 30th May: decide project plan.
- 31th May - 20th June: test scaffolding for Maven that runs JUnit, JMock, HyperSQL, and Jetty for the tests. Create the 3 base classes: an Abstract Functional Test, an Abstract Integration Test, and an Abstract Unit Tests. Optionally there might be integration with Hudson/SONAR.
- 14th June - 11th July: Add Contiperf to the set for performance testing. Start generating unit tests for DSpace API.
- 12th July (Mid Term Evaluation): By this day a number of selected packages from DSpace API should have tests
- 12th July - 8th August: Integrate Selenium into the scaffolding. Prepare tests for selected XMLUI functionalities.
- 9th August: By this day we should have functional tests on the UI on selected functionalities
- 9th August - 16th August (Final Evaluation): code fixes and documentation related to the project
Tools
- The Continuous Integration server will be Hudson.
Wiki Markup SONAR \[[http://www.sonarsource.org/|http://www.sonarsource.org/] \] will be the code quality management tool
- All tests will be run automatically by Maven
- Embedded webserver will be Jetty
Wiki Markup Embedded database will be HyperSQL \[[http://hsqldb.org/|http://hsqldb.org/] \]
- Functional Tests will use Selenium
- Unit Tests and Integration Tests will use Junit
- JMock will be used as mocking framework
- HTMLUnit may be used if required
- Performance Tests will use ContiPerf
...