Month | Activity | Assignee | Status | Notes | |
---|---|---|---|---|---|
October | Create and review project plan | David Pilot | Complete | ||
October | Establish functional requirements
| Pilot David Alan | In progressComplete | Gap analysis is complete. Features have been prioritized. | |
October | Establish metadata mapping and remediation scope and timelines | David Pilot | Complete | Scope and timelines established at 2020-10-08 meeting | |
November | Complete metadata remediation work | Pilot | In progressComplete | ||
December | Map metadata and data models
| Pilot David | In progressComplete | ||
November | Document the mapping process | David Pilot | In progressComplete | ||
November | Run test migration
| Alan | To doComplete | ||
January February | Install and configure Islandora 8 using ISLE
| Born Digital | To doComplete | ||
February March | Complete data migration
| Alan | To doComplete | Data migration began in the summer of 2021; it was restarted from scratch in August 2021 to deal with problems in storage. Ingest took several months due to very large sets of data and to issues that emerged with duplicated taxonomy terms that required remediation. All collections were ingested by November 2021. | |
February March | Document the migration process | David Alan Pilot | To doComplete | ||
March April | Complete software updates to meet functional requirements
| Alan Born Digital | To doComplete | Additional work to fix the handling of access and to ensure satisfactory speed of the site extended from completion of migration in November 2021 through February 2022 – this included an update to Drupal 9 on both production and staging. | |
April May | Complete acceptance and performance testing
| Pilot Danny Alan | To doComplete | Following the concurrent testing during migration, the main QA and performance testing period was from November 2021 through February 2022. Whitman signed off on the site on March 11, and cutover was March 23, 2022. | |
May | Complete process documentation
| David Pilot | To doComplete | Documentation continued through migration and post-migration testing into 2022. | |
May | Create case study
| David Pilot | To doComplete | Creation of the case study continued through migration and post-migration testing into 2022. |
Milestones
- Metadata and data model mappings: December
- Islandora 8 installation: January/February
- Complete data migration: March