title7.1 Release Plan

Tentative Release Schedule:

  • Thursday, September 23 (PR Create Date): every PR wanting to get into 7.1 should be created. Any created by this date are "guaranteed" in 7.1. Anything after may not be included in 7.1.
  • Sept 23 - Oct 14 (PR Final Reviews): code reviews & PR updates
  • Thursday, Oct 14 (PR Merge Date): every PR getting into 7.1 must be merged.
  • Monday, Oct 25: Internal/Early release goal.  If possible, we'd like to release 7.1 in late Oct.
  • Monday, Nov 1: Public Release Deadline. 7.1 must be announced/released by this date.

Ongoing/Weekly tasks:

7.1 likely new features (list not final)

...

  • (30 mins) General Discussion Topics
    1. Review status of all features likely in 7.1 (see list above).
    2. Demo site performance issues? https://demo7.dspace.org/  Is anyone else having slow load times & occasional "out of memory" crashes?
    3. (Other Topics?)
  • (30 mins) Planning for next week
    • Review the Backlog Board - Are there any tickets here stuck in the "Triage" column?  We'd like to keep this column as small as possible.
    • Review the 7.1 Project Board - Assign tickets to developers & assign PRs to reviewers.
      • Paid (by DSpace project) developers must keep in mind priority. If new "high" or "medium" priority tickets come in, developers should move effort off of "low" priority tasks.
      • Volunteer developers are allowed to work on tickets regardless of priority, but ideally will review code in priority order.

...