Date | Milestone | What it means |
---|---|---|
October 29November 12 | Deadline for feature pull requests | If you wish to contribute features to DSpace 6.0, you must submit a pull request by this date. |
November 418 | Weekly developers' meeting devoted to review of feature pull requests for 6.0 | The entire hour's meeting will be used to discuss proposed features submitted by the deadline. |
November 1125 | Weekly developers' meeting devoted to review of feature pull requests for 6.0 | The entire hour's meeting will be used to discuss proposed features submitted by the deadline. |
November 20December 11 | Feature freeze | DSpace 6.0 is considered feature-complete on this date. Only bugfixes will be pulled between this date and final release. |
November 24December 15 | Release Candidate 1 tagged | A DSpace 6.0 Release Candidate will be available for wider testing. |
December 07-18January 4-15, 2016 | Testathon | Intensive public testing of the 6.0 Release Candidate is invited. The Release Team will focus on getting problems resolved. |
December 23January 20, 2016 | Release Candidate 2 tagged | An updated DSpace 6.0 Release Candidate will be available for wider testing. |
JanuaryFebruary/February March 2016 | DSpace 6.0 is publicly released | DSpace 6.0 is released for download and general use. |
...