Date | Milestone | What it means |
---|---|---|
October 07 | Deadline for feature pull requests | If you wish to contribute features to DSpace 4.0, you must submit a pull request by this date. |
October 09 | Weekly developers' meeting devoted to review of feature pull requests for 4.0 | The entire hour's meeting will be used to discuss proposed features submitted by the deadline. |
October 16 | Weekly developers' meeting devoted to review of feature pull requests for 4.0 | The entire hour's meeting will be used to discuss proposed features submitted by the deadline. |
October 21 | Feature freeze | DSpace 4.0 is considered feature-complete on this date. Only bugfixes will be pulled between this date and final release. |
October 31 | Release Candidate 1 tagged | A DSpace 4.0 Release Candidate will be available for wider testing. |
November 04-15 | Testathon | Intensive public testing of the RC is invited. The Release Team will focus on getting problems resolved. |
November 21 | Release Candidate 2 tagged | An updated DSpace 4.0 Release Candidate will be available for wider testing. |
December 04 | DSpace 4.0 release tagged | DSpace 4.0 is release released for general use. |