Comment: Adding updated schedule based on email from Sands

...

Note

It has been decided that DSpace 3.0 will be released in Fall 2012. The exact date is still being worked out, but will likely be in October/November.

Release Timeline (PROVISIONAL): 

  • August

...

  • 24, 2012 : Feature

...

  • /Code Submission Deadline - New features must be submitted as a GitHub Pull Request by this date. Any new features submitted after this date will not be considered for 3.0.
  • August 31

...

  • , 2012 : Final Documentation

...

  • Due Date - Initial documentation for all new features is due.
  • September 7, 2012 : Feature Freeze - This is an internal deadline for the Committers. This is the date by which the Release Team and Committers will have reviewed via Pull Request, and accepted or rejected all contributions made for the 3.0 release. Rejected code has to wait for the next version of DSpace (or is suggested to be released separate from the current release as a "third party add-on", if applicable).
  • September 14

...

  • , 2012 : Release Candidate 1 Release

...

  • September

...

  • 17-

...

  • 28, 2012 :

...

  •  Test-a-thon
  • October 12

...

  • , 2012 : Release Candidate 2 Release

...

  • October

...

  • 15-

...

  • 24, 2012 : Final Testing / Bug Fixing

...

  • October

...

  • 26, 2012 : 3.0 Final Release

Release Process needs to proceed according to the following Maven release process: Release Procedure