- Weekly sprint for July 12 created. Open tickets for July 5th moved to this sprint
- July 12 sprint is particularly heavy for Naomi. Some of the tickets like the Hypatia VM requests are currently being worked on by sys-admin team
- Gould data modeling beginning today. Need to sync up the data modeling and fixture creation and ensure these are appropriately ticketed in JIRA
- Mark will be working on ArchiveSpace project. Will stay involved with Hypatia but there will be increasing involvement of other DAs like Simon and Gretchen on the Hypatia-tech call when Mark isn't able to attend