title7.2 3 Release Plan

Release Schedule (TENTATIVE, may need revising based on OR2022 plans):

  • (tick) Thursday, Dec 23 Apr 28 (PR Creation Deadline): All new feature (or larger) PRs should be created by this date. (Smaller bug fixes are welcome anytime)
  • (tick) Thursday, Jan 20 May 19 (Review/Test Deadline): All code reviewers or testers should submit their feedback by this date. Code reviews must be constructive in nature, with resolution suggestions. Any code reviews submitted AFTER this date will be considered non-blocking reviews. This means feedback received after Jan 20 is optional to address (unless the team or PR developer decides it is required).
  • (tick) Friday, Jan 28 May 27 (PR Merge Deadline): All new feature PRs should be merged by this date. (Bug fixes can still get in, as long as they are small or important)
  • Week of Monday, Jan 31May 30: Internal / Early release goal. If possible, we'd like to release 7.2 3 in late January May or first week of FebJune.
  • Monday, Feb 7June 6: Public Release Deadline. 7.2 3 must be announced/released by this date.

Ongoing/Weekly tasks:

...

  • (30 mins) General Discussion Topics
    1. Open Repositories 2022 (June 6-9 in Denver). Who is planning to attend? What would we want to plan for DSpace 7?
      1. DSpace 7.2/7.3 workshop: Leaning towards holding an online workshop/webinar instead of a workshop at OR2022. 
      2. DSpace 7.2/7.3 talks: Team noted it would be best to have at least one DSpace 7 talk at OR2022 in order to provide an update to the OR community.  Additional talks might be moved online perhaps alongside the online workshop? 
    2. Review tentative 7.3 Release Schedule above. This is based on a new 4-month release window, but could conflict with OR2022 plans.
    3. Planning / Prep for 7.3.  Feel free to start claiming (high priority) tickets from either of these two boards:
      1. 7.3 Board (all incomplete/unclaimed 7.2 tickets have been moved to here)
      2. 7.x Tier 1 Board (all remaining highest priority features)
    4. (Other Topics?)
  • (30 mins) Planning for next week
    • Review the Backlog Board - Are there any tickets here stuck in the "Triage" column?  We'd like to keep this column as small as possible.
    • Review the 7.2 3 Project Board - Assign tickets to developers & assign PRs to reviewers.
      • Paid (by DSpace project) developers must keep in mind priority. If new "high" or "medium" priority tickets come in, developers should move effort off of "low" priority tasks.
      • Volunteer developers are allowed to work on tickets regardless of priority, but ideally will review code in priority order.

...