- Server provisioned with sufficient space and operating environment for Islandora 8 and migrated data
- A decision made with regard to the migration utility to be used
- Exported Islandora 7 data
- List of functional requirements for Islandora 8
- List of metadata schemas and fields
- List of data models
Timelines
Month | Activity | Assignee | Status | Notes |
---|---|---|---|---|
October | Create and review project plan | David Pilot | Complete | |
October | Establish functional requirements
| Pilot David Alan | In progress | Gap analysis is complete. Features have been prioritized. |
October | Establish metadata mapping and remediation scope and timelines | David Pilot | Complete | Scope and timelines established at 2020-10-08 meeting |
November | Complete metadata remediation work | Pilot | Complete | |
December | Map metadata and data models
| Pilot David | Complete | |
November | Document the mapping process | David Pilot | Complete | |
November | Run test migration
| Alan | Complete | |
January February | Install and configure Islandora 8 using ISLE
| Born Digital | Complete | |
February March | Complete data migration
| Alan |
In progress | ||||
February March | Document the migration process | David Alan Pilot | In progress | |
March April | Complete software updates to meet functional requirements
| Alan Born Digital |
In progress | ||
April May | Complete acceptance and performance testing
| Pilot Danny Alan |
In progress | ||
May | Complete process documentation
| David Pilot |
In progress | ||||
May | Create case study
| David Pilot | In progress |
Milestones
- Metadata and data model mappings: December
- Islandora 8 installation: January/February
- Complete data migration: March
- Front-end configuration to meet functional requirements: April
...