Month | Activity | Assignee | Status | Notes |
---|---|---|---|---|
October | Create and review project plan | David Pilot | Complete | |
October | Establish functional requirements
| Pilot David Alan | In progress | Gap analysis is complete. Features have been prioritized. |
October | Establish metadata mapping and remediation scope and timelines | David Pilot | Complete | Scope and timelines established at 2020-10-08 meeting |
November | Complete metadata remediation work | Pilot | Complete | |
December | Map metadata and data models
| Pilot David | Complete | |
November | Document the mapping process | David Pilot | In progressComplete | |
November | Run test migration
| Alan | In progressComplete | |
January February | Install and configure Islandora 8 using ISLE
| Born Digital | In progressComplete | |
February March | Complete data migration
| Alan | To do | |
February March | Document the migration process | David Alan Pilot | To doIn progress | |
March April | Complete software updates to meet functional requirements
| Alan Born Digital | To do | |
April May | Complete acceptance and performance testing
| Pilot Danny Alan | To do | |
May | Complete process documentation
| David Pilot | To do | |
May | Create case study
| David Pilot | To doIn progress |
Milestones
- Metadata and data model mappings: December
- Islandora 8 installation: January/February
- Complete data migration: March
- Front-end configuration to meet functional requirements: April
...